Slab Electrical Work Before Casting: Checklist and Materials List for Bengaluru Homes
By WireBolt Team · Updated · 6 min read
Quick answer
Before the slab is cast, every ceiling fan, light and spotlight point needs its box and conduit fixed and tied to the steel. Use HMS (heavy) pipe, seal every joint and close every box and pipe end, because nothing can be added once the concrete is poured. Getting it right costs very little; fixing a missed point later means breaking the ceiling.
The slab is cast once. Whatever electrical piping is inside it when the concrete goes in stays there for the life of the house, and whatever is missing can only be added by breaking the ceiling. That's why experienced builders in Bengaluru treat the few hours of electrical work before casting as one of the most important steps in the whole construction.
The good news: it's simple and cheap if you plan it. For one floor of a typical 30x40 house, all the pipes, boxes and fittings in the slab cost a tiny fraction of what the slab itself costs. This guide gives you the checklist, the materials list and the quantities, so nothing is missed on casting day.
What goes wrong when slab electrical work is rushed
These are the problems electricians are called back for, months later:
- A fan or light point was forgotten. The room's only option is surface wiring or a false ceiling.
- A pipe got blocked with concrete slurry. No wire can be pulled through it, so the run has to be abandoned.
- A thin pipe was crushed under the concrete or a worker's boot. Same result.
- A fan box was fixed off-centre or tilted. The fan never hangs straight in the middle of the room.
Each one costs a day of chasing, plastering and repainting, plus the mess, in a house you've just finished. Every one of them can be prevented for a few rupees on casting day.
When the electrical work happens
- Shuttering is done and the bottom reinforcement is laid.
- Electrician lays the conduit, boxes and drops: usually a day's work for one floor of a house.
- Top reinforcement (if any) goes in; the engineer checks the steel.
- Final electrical check (the checklist below), then casting.
Book your electrician and get the material on site at least a day before casting, so the work isn't squeezed into the morning of the pour.
Step 1: Mark every point on the shuttering
Walk the slab with the floor plan and mark with chalk:
- Ceiling fans: centre of each room, hall and dining area. Mark a fan point in every bedroom even if you don't plan a fan yet; a fan box costs very little now; adding one later costs thousands.
- Ceiling lights and spotlights, placed so they're not directly above a fan (the blades cause a flicker).
- Drops: where pipes come down from the slab into the walls to each switchboard.
- Future points: balcony and sit-out lights, a porch light, CCTV cameras and a Wi-Fi access point. Data and CCTV cables need their own pipe, separate from power.
Step 2: The slab electrical materials list
| Item | Use it for | Choose |
|---|---|---|
| PVC conduit pipe, HMS | All runs inside the slab | 19 mm for lights and fans, 25 mm where circuits share a pipe |
| Fan box (heavy, metal) | Every ceiling fan point | One per fan point, with a hook |
| Junction boxes | Light points and where pipes branch | 3-way or 4-way, same size as the pipe |
| Deep metal junction box | Points where several pipes meet | Extra room for joints |
| Spotlight junction box | Concealed spotlight points | One per spotlight |
| Bends | Every corner and drop | Ready-made HMS bends |
| Collars | Joining two lengths in a straight line | Same size as the pipe |
| Conduit solvent | Sealing every joint | 1 tin per floor (2 for large floors) |
| Fan box covers | Closing fan points after plastering | One per fan box |
| Binding wire, tape, paper | Tying pipes, sealing boxes | From your site stock |
All of it is in our pipes, conduits and accessories range. Not sure about sizes and grades? See the conduit pipe size guide, and our guides to fan boxes and to conduit fittings.
Step 3: Fix it properly (the rules electricians follow)
- HMS pipe only inside the slab. MMS saves only a few rupees per length and risks a crushed pipe you can never replace.
- Lay pipes on top of the bottom steel and tie them with binding wire about every metre, so they can't float or shift during the pour. Never below the bottom steel.
- Don't cut or bend the reinforcement to make room for pipes or boxes.
- Spread pipes out. Don't bunch many pipes side by side; concrete must flow all round them. Where many runs meet, use a deep junction box.
- No more than two bends between boxes, or the wire won't pull through later.
- Solvent-cement every joint: pipe to collar, bend and box.
- Close every opening: fill each box tightly with paper or thermocol and tape it, tape every open pipe end at the drops.
- Fix fan boxes level and centred, tied to the steel, with the hook in place.
- Leave drops long enough to reach well into the wall below, and mark where each one is.
The final check before casting
Print this or keep it on your phone, and tick it off with your electrician the evening before the pour:
- ☐ Every fan point has a heavy fan box, level and centred
- ☐ Every light and spotlight point has its box
- ☐ Future points (balcony, porch, CCTV, Wi-Fi) are piped
- ☐ All pipes inside the slab are HMS grade
- ☐ All pipes are tied to the steel; none lie below the bottom steel
- ☐ Every joint is solvent-cemented
- ☐ Every box is filled and taped; every pipe end is sealed
- ☐ No run has more than two bends between boxes
- ☐ Drops are marked at each switchboard position
- ☐ Photos taken of the whole slab with measurements
- ☐ An electrician will be on site during casting
How much material for your house? (Bengaluru plot sizes)
Typical quantities for one floor of an independent house. Use them to plan the order, then confirm with your layout.
| Plot (typical floor) | Fan boxes | Light / junction boxes | 19 mm HMS pipe (3 m) | 25 mm HMS pipe (3 m) | Bends | Collars | Solvent |
|---|---|---|---|---|---|---|---|
| 30x40 (≈1,000–1,100 sq ft, 2BHK) | 4–5 | 12–16 | 25–35 | 3–6 | 30–40 | 15–25 | 1 |
| 30x50 (≈1,300–1,400 sq ft, 3BHK) | 5–6 | 16–20 | 35–45 | 5–8 | 40–50 | 20–30 | 2 |
| 40x60 (≈2,000–2,200 sq ft) | 7–9 | 22–30 | 55–70 | 8–12 | 60–80 | 30–45 | 2–3 |
Casting day
- Keep the electrician on site during the pour to fix any pipe knocked loose by workers or the vibrator.
- After the shuttering comes off, remove the filling from every box and push a fish wire through each run. A blocked pipe found now can still be re-routed before plastering.
- Fit fan box covers until the fans go up.
Get everything on site in one delivery
Casting dates don't wait for a missing bag of bends. Order the full list together:
- Same day: order by 7 PM and it's delivered by 9 PM.
- Next morning: later orders arrive by 11:30 AM.
- Bulky items: pipes come by 3-wheeler, anywhere in Bengaluru.
This guide is general information for homes in Bengaluru. Electrical work should be done by a licensed electrician who can check your actual load, wiring and supply. Last checked 19 November 2026.